We’re continuing to invest in Phipps Bridge, Mitcham, with a major improvement programme that began on 31 March 2026.
This is a multi-year project covering 11 residential blocks, with works being completed in carefully planned phases. The overall completion date will be confirmed as the programme progresses.
Blocks Include:

A wide range of improvements are being carried out to help protect the buildings, improve residents’ homes and enhance the communal areas. These include:

These improvements will help to:

Roofing works are complete at Merrow Court, Ripley Court, Bramley Court, Albury Court and Brooklands Court. Windows are in progress on all of these blocks. Cranleigh Court scaffolding is being erected prior to the roof works commencing. The next block to start will be Ewhurst Court but this will not be until early 2027.
Residents affected by each phase will receive advance notice of when work is due to start on their building and when access to individual homes is required.
We appreciate that large-scale improvement works can cause some temporary disruption, and we’d like to thank residents for their patience and cooperation. We’ll continue to provide updates as the programme progresses and will keep residents informed of key milestones throughout the project.


Planned Investment Manager in South London

Lead Planned Investment Manager
The 20-year partnership with United Infrastructure provides stability, building strong relationships across management, site teams, and subcontractors, benefiting all stakeholders.


Site Manager
Russ is an experienced site manager with a background in key finishing trades. He is responsible for ensuring our supply chain work safely, efficiently and collaboratively to complete the works. Russ is also responsible for temporary works and quality control.

Resident Liaison Officer
Kim is an experienced RLO with over 20 years service with United Infrastructure. Kim covers the Merton region predominantly, and is responsible for all resident engagement, newsletter updates and general point of contact for key updates for works that are in progress.
If you have any questions or would like support regarding the major works, please don’t hesitate to get in touch, by choosing one of the options below.